PERT (method for estimating)
Program Evaluation and Review Technique
my attention. I questioned the validity of this method for estimating at first but later realized it is fairly accurate on projects with many activities. I’m not sure you can expect accuracy on a single activity.
Optimistic - shortest time in which the activity can be completed.
Most likely - highest probability guess.
Pessimistic - longest that might be required.
FORMULA:
Optimistic + (4 x Most likely) + Pessimistic
Estimate = -----------------------------------------------------------
6